Timeline


Our Milestones

December 8, 2012 - Signed Contract

December 13, 2012 – Preliminary Approval from First Home Mortgage

December 12, 2012 - Met SR to go over options

December 22, 2012 – Picked our brick and colors

December 27, 2012 – Picked Flooring/carpet options

December 29, 2012 – picked multimedia /audio options thru CV security

January 24, 2013 – Lot change from 14 to 6

February 4, 2013 - Pre-construction Meeting

February 18 – Estimated time for construction to start!

February 18, 2013 - Lot was staked

February 20, 2013 - Backhoe delivered to lot

February 22, 2013 -  Lot is cleared, placed the gravel driveway and new Silt Fence was installed.

February 23, 2013 - Brick color changed

__________________________________________________________________________________

Start of Construction

March 4 - 9, 2013

Day 1- Excavation

Day 2- Footers

Day 3- Nothing  SNOW

Day 4- Foundation Walls Framed

Day 5- Foundation Walls Poured

Day 6- Foundation forms removed

March 10- 16, 2013

Day 7- Nothing

Day 8- Nothing

Day 9- Waterproofing started.

Day 10- Nothing

Day 11- Plumbing / Locked our Rate 3.5%

Day 12- Nothing

Day 13-  Waterproofing finished and gravel started to be poured

March 17- 23, 2013

Day 14- Nothing

Day 15- Nothing

Day 16- Backfilled started / USDA Approval!!

Day 17- Underground Plumbing Inspection Approved!

Day 18-  Nothing

Day 19- Wood Delivered!!

Day 20-  gravel poured on basement and garage floors

March 24- 30, 2013

Day 21- Forms and rebar placed for cement floors in basement and garage

Day 22-nothing

Day 23- Inspection of floors and rebar Approved

Day 24- Cement Floors poured

Day 25- More wood delivered

Day 26-  Roof Delivered

Day 27- Nothing

March 31-  April 6, 2013

Day 28-  Easter Nothing

Day 29- Stinky Nothing PM/SR sucks no communication

Day 30-  Beams laid and Framing started

Day 31- First floor walls done and interior walls almost done!!

Day 32-  First floor completed and floor started on 2nd Floor

Day 33-  2nd Floor flooring completed

Day 34-  Nothing

April 7- 12, 2013

Day 35-  Nothing

Day 36- 2nd Floor walls up

Day 37- Roof Trusses installed

Day 38-  Half of roof covered with plywood

Day 39-  Roof  covered in Plywood shingles delivered

Day 40-  Rain delay dumpster delivered

Day 41-  Shingles installed.

April 14- 20, 2013

Day 42- Nothing

Day 43- Steps insulation started, garage doors framed

Day 44-  Garage steps and trim installed and cleaned up!

Day 45- Windows, doors and wrap started.

Day46-  More windows installed. 1st layer of wrap

Day 47- Main stairs installed, windows taped, HVAC markings

Day 48- Nothing

April 21- 27

Day  49- Nothing

Day 50- Brick and scaffolding delivered

Day 51- Nothing

Day 52-  Electrical started, PVC pipes delivered, final wrap installed. work order change to include eyeball lights and stair stain to cherry. Met with PM to go over Master bath framing

Day 53-  Brick started, plumbing installed as well as bathtubs & hot water heater

Day 54-  More Brick

Day 55-  More Brick

April 28- May 4th

Day 56-  Nothing

Day 57- Nothing

Day 58- Brick, HVAC and more electrical work

Day 59-  Brick finished

Day 60- More electrical work

Day 61- Windows fixed in Solarium

Day 62-  Nothing

May 5th -  May 11th

Day 63- Nothing

Day 64- Pre wiring meeting with CV Security, Sprinklers started, more electrical work

Day 65-  Wrote verses on walls

Day 66-  Finished verses on walls Finished electrical work

Day 67-  Pre Drywall meeting, sprinklers finished

Day 68-  Electrical inspection Passed/ Corrections made from pre drywall meeting

Day 69-  Nothing

May 12th- May 18th

Day 70- Nothing

Day 71-  Inspections for Electrical and Framing

day 72- Insulation installed

Day 73-  Insulation installed

Day 74-  Failed Energy test, Dirt hauled away

Day 75- Passed Energy star test

Day 76-  Drywall Installed

May 19th- May 25th

Day 77- Nothing

Day 78-  Siding started

Day 79- Mudded

Day 80- Siding, Trim and shutters finished

Day 81-  Mudded and Sanded, interior doors, trim and paint delivered.

Day 82-  Cabinets delivered, trim installed

Day 83-  Nothing

May 26th- June 2nd

Day 84- Nothing

Day 85-  Painting, water ran to house

Day 86- Cabinets installed

Day 87- Electrical work

Day 88-  Painting

Day 89- Nothing

Day 90- Nothing

June 3rd-  8th

Day 91-  Tile started, railings started, gas line ran to house

Day 92-  Tile finished, fixtures installed, sink faucets, carpet installed

Day 93- Driveway and front steps poured, outside units installed

Day 94- Railings finished, more electrical work, appliances started

Day 95- Paint touched up, more appliances installed, closet shelves installed, more electrical

Day 96-  Nothing

June 9th- 15th

Day 97- Gutters Installed

Day 98- Nothing

Day 99- Fridge installed

Day 100- Sod installed, Door painted, 2nd coat of stain on steps

Day 101-  Inspections

Day 102- U&O and Final Appraisal!

Day 103- Nothing

June 16th- 18th

Day 104- Nothing

Day 105- Final Walk Thru

Day 106- June 18th Closing 10:00 AM!!!!!
________________________________________________________________________

Living in Home

June 19, 2013



 